When adding wall sweeps to the structure of a wall in Revit and syncing to Twinmotion the sweeps will not always sync especially if I change a different element of the the file in Revit. The only solution I’ve found is to select all my walls in the project with the sweep, copy them, delete them, paste back into place, then sync to Twinmotion, if that’s not inconvenient enough, all the materials are then removed from the walls and I have to remember what materials go where. How has this issue not been resolved especially in 2025?? This issue makes the program almost unusable, hours I’ve spent learning it but because of this huge issue I may have to look into other programs.