Revit Phasing overrides Twinmotion materials

Hello

I have multiple phases in Revit and when I direct link sync with Twinmotion, every material is overriden to only two : One White and another New Existing which is gray

After this issue, i found a possible solution and I created a special Phase filter just for Twinmotion, with New - By category - Existing By category, Demolished - Not displayed, Temp - Not displayed

I have closed every other Revit 3d view, reset the direct link folder, even deleted it, restarted the PC, etc, but I still get only two materials in Twinmotion.

No I just realized that If I create a new element in Revit, it will be synced with the right material but all the other ones stay the same.

What is the way to do it? Thanks!

LATER EDIT

It looks like it takes every previous phase as Existing and applies that override because i created the Twinmotion phase the last one.
Is there a way to correct it/workaround? How to setup Revit for this?

Ok, now I have disabled the Revit Phasing material override and after restarting both TM and Revit, It looks like i got the correct materials.

Does that mean It cannot work while using the Revit phasing material override?

I’m exploring the Revit to Twinmotion workflow for my firm and keep experience this issue as well. It seems like every time I open my project, some materials work and others grey out as existing. I set the phase filer to “Show Complete” for the 3D view I have dedicated to Twinmotion and sync from that view each time. Is there a clearly explained process? I’ll be digging around on Autodesk’s site as well. Thanks all.