I'm wandering if I could achieve a construction simulation in Twinmotion by recreating something similar to a real schedule (Gantt chart) using Tracks and phases. Usually our schedules are quite comprehensive and large and I'm interested is there any limit of phasing Tracks that can be added to a project? Thanks
Hi ,
There is no limit the number of phases or tracks you can have in a phasing group. The only limit with phasing groups is the total duration of the group being capped at six years after the start date, so a phasing group starting in 2023 can only go as far as 2029.
Best,
Raghib